#1 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 27 July 2006 - 07:50 AM

Maybe it's just my OCD acting up, but I'd like to have this thread be updated (similar to the building height ranking thread) to show when all the numerous 'significant' projects are expected to be completed (even if just proposed - just not a 'rumor').  The ones I know off hand are:

Fidelity renovation (old AMEX):                                 August 2006
GTech Headquarters building:                                 September 2006
Hilton Renovation:                                           September 2006
Providence Renaissance Hotel (Masonic Temple):     December 2006
ALCO phase 1 (first 5 buildings - office & retail space):     December 2006
Westin II:                                                        June 2007
Waterplace:                                                August 2007
Hilton parking garage:                                         December 2007
T. F. Green Airport Terminal Renovations:     December 2007
Wickenden St. Comm CTR & Library:            December 2007
Dynamo House & Heritage Harbor Museum:     October 2008
OneTen Westminster:                                  December 2008
Dunkin Donuts Center renovations:               December 2008
ALCO 'final' phases:                                    December 2008
Warwick Intermodal Transportation Center:  October 2009
Empire at Broadway:                                              December 2010


still need:
last phases of the Foundry
Federal Hill condos and hotel proposals (that are more than just rumors)
Parcel 12??
etc.

Edited by mental757, 29 July 2006 - 08:24 AM.


 

#2 CtownMikey

CtownMikey

    Burg

  • Members+
  • PipPipPipPipPip
  • 1,969 posts
  • Location:Providence

Posted 27 July 2006 - 08:50 AM

Gtech is the end of next month and E@B is the end of 2010. Masonic should be completed this winter. The Hilton renovation should be done for September of this year.

The major project for 06' is really Gtech when they add the 500+ workers to the city soon and we hopefully get a projo article on their response to working in Providence..... that, and the AMEX fidelity deal. The entire block is going to add about 1000 daily workers :)

Waterplace and The Westin II are going to be finished in 07' probably both in early fall.


Cotuit would be the master at doing this though :)

#3 Statesman

Statesman

    Unincorporated Area

  • Members
  • PipPip
  • 57 posts
  • Location:Providence

Posted 27 July 2006 - 09:07 AM

The actual name for the Masonic Temple project is the Providence Renaissance Hotel and it's slated to be done this winter, yep.

#4 brick

brick

    Burg

  • Members+
  • PipPipPipPipPip
  • 1,216 posts
  • Location:Land of Milk and Honey

Posted 27 July 2006 - 09:20 AM

I don't know that it actually deserves a spot on the list, but the AMEX building is already occupied by a handful of fidelity employees and just walking around down there feels a lot different with a tenant that actually cares about the surroundings.  I don't know if they are going to have an official opening for their remodel, though.  Speaking of which, the place doesn't look too bad now that it's been remodelled.

#5 mr2448

mr2448

    Whistle-Stop

  • Members+
  • PipPipPip
  • 271 posts
  • Location:chepachet, rhode island

Posted 27 July 2006 - 07:45 PM

View Postbrick, on Jul 27 2006, 09:20 AM, said:

I don't know that it actually deserves a spot on the list, but the AMEX building is already occupied by a handful of fidelity employees and just walking around down there feels a lot different with a tenant that actually cares about the surroundings.  I don't know if they are going to have an official opening for their remodel, though.  Speaking of which, the place doesn't look too bad now that it's been remodelled.

Do these people also play Polo?

Mark

#6 Dan

Dan

    Hamlet

  • Validating
  • PipPipPipPip
  • 518 posts
  • Location:Providence, RI | Mount Pleasant

Posted 27 July 2006 - 08:16 PM

Quote

[when all the numerous 'significant' projects are expected to be completed]ALCO phase 1 (first 5 buildings - hotel & offices):     December 2006

The hotel is new construction, no?  Do we even know where in the complex the hotel is to be built?

It has to be 12/2007, 6 months can't possibly be enough time!

Edited by Dan, 27 July 2006 - 08:17 PM.


#7 runawayjim

runawayjim

    Metropolitan Area

  • Members+
  • 8,059 posts
  • Location:Providence - Elmhurst

Posted 28 July 2006 - 09:07 AM

i think the 110 end date is sometime in the second half of 2008.

#8 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 28 July 2006 - 09:25 AM

View PostDan, on Jul 27 2006, 10:16 PM, said:

The hotel is new construction, no?  Do we even know where in the complex the hotel is to be built?

It has to be 12/2007, 6 months can't possibly be enough time!

from the projo:

"The development is nicknamed ALCO, and its insignia was borrowed and updated from American Locomotive Works' letterhead. Struever hopes to complete the first phase of the project, which includes a hotel and office buildings, by the end of the year, and finish the entire project by 2008."

Of course, they could be mistaken...



View Postrunawayjim, on Jul 28 2006, 11:07 AM, said:

i think the 110 end date is sometime in the second half of 2008.

OK - I'll roll with Dec 2008 until we have a better idea on the timing...

#9 runawayjim

runawayjim

    Metropolitan Area

  • Members+
  • 8,059 posts
  • Location:Providence - Elmhurst

Posted 28 July 2006 - 09:27 AM

View Postmental757, on Jul 28 2006, 11:25 AM, said:

from the projo:

"The development is nicknamed ALCO, and its insignia was borrowed and updated from American Locomotive Works' letterhead. Struever hopes to complete the first phase of the project, which includes a hotel and office buildings, by the end of the year, and finish the entire project by 2008."

Of course, they could be mistaken...
OK - I'll roll with Dec 2008 until we have a better idea on the timing...

you should check out the development maps... they have all the start and end dates for the projects.

#10 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 28 July 2006 - 09:28 AM

what's the link - on the SBER site???

#11 runawayjim

runawayjim

    Metropolitan Area

  • Members+
  • 8,059 posts
  • Location:Providence - Elmhurst

Posted 28 July 2006 - 09:32 AM

View Postmental757, on Jul 28 2006, 11:28 AM, said:

what's the link - on the SBER site???

it's on the urban planet site... development maps

#12 Cotuit

Cotuit

    Megalopolis

  • Global Moderators
  • 13,396 posts
  • Location:State of Rhode Island and Providence Plantations

Posted 28 July 2006 - 09:49 AM

View Postrunawayjim, on Jul 28 2006, 11:27 AM, said:

you should check out the development maps... they have all the start and end dates for the projects.

Haha, I did that and totally forgot that I put end dates on a lot of them. Some are a little off target now though.

#13 gregw

gregw

    Hamlet

  • Members+
  • PipPipPipPip
  • 857 posts
  • Location:Summit, Providence

Posted 28 July 2006 - 10:06 AM

I thought that the final phase of the ALCO project--the Nicholson File/Capco property on Acorn St. south of the river--was going to be done pretty far down the road--like 2010 or something.

#14 Cotuit

Cotuit

    Megalopolis

  • Global Moderators
  • 13,396 posts
  • Location:State of Rhode Island and Providence Plantations

Posted 28 July 2006 - 10:37 AM

The most important question is when is Happy Endings Dessert Spa having its grand opening?

#15 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 28 July 2006 - 12:10 PM

View Postrunawayjim, on Jul 28 2006, 11:32 AM, said:

it's on the urban planet site... development maps

cool - thanks, I hadn't found that page here yet!

I still would like to have a single listing for all the major projects versus having to click on each site though.  Perhaps Cotuit could help me keep the dates up to speed in this one too???

#16 Garris

Garris

    Town

  • Members+
  • 3,228 posts
  • Location:Providence, RI (Wayland Square)

Posted 28 July 2006 - 12:44 PM

You can add the Wickenden St. Bath House/Community Center/Library for the end of 2007...

- Garris

#17 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 28 July 2006 - 02:22 PM

View PostGarris, on Jul 28 2006, 02:44 PM, said:

You can add the Wickenden St. Bath House/Community Center/Library for the end of 2007...

- Garris


done.   :D  :thumbsup:

#18 mental757

mental757

    Burg

  • Members+
  • PipPipPipPipPip
  • 2,050 posts
  • Location:Kent County

Posted 03 August 2006 - 02:27 PM

View Postmental757, on Jul 27 2006, 09:50 AM, said:

Maybe it's just my OCD acting up, but I'd like to have this thread be updated (similar to the building height ranking thread) to show when all the numerous 'significant' projects are expected to be completed (even if just proposed - just not a 'rumor').  The ones I know off hand are:

Fidelity renovation (old AMEX):                                 OPEN! 8/2/06
GTech Headquarters building:                                 September 2006
Hilton Renovation:                                           September 2006
Providence Renaissance Hotel (Masonic Temple):     December 2006
ALCO phase 1 (first 5 buildings - office & retail space):     December 2006
Westin II:                                                        June 2007
Waterplace:                                                August 2007
Hilton parking garage:                                         December 2007
T. F. Green Airport Terminal Renovations:     December 2007
Wickenden St. Comm CTR & Library:            December 2007
Dynamo House & Heritage Harbor Museum:     October 2008
OneTen Westminster:                                  December 2008
Dunkin Donuts Center renovations:               December 2008
ALCO 'final' phases:                                    December 2008
Warwick Intermodal Transportation Center:  October 2009
Empire at Broadway:                                              December 2010

still need:
last phases of the Foundry
Federal Hill condos and hotel proposals (that are more than just rumors)
Parcel 12??
etc.

#19 runawayjim

runawayjim

    Metropolitan Area

  • Members+
  • 8,059 posts
  • Location:Providence - Elmhurst

Posted 03 August 2006 - 02:42 PM

View Postmental757, on Aug 3 2006, 04:27 PM, said:

Fidelity renovation (old AMEX):                                 OPEN! 8/2/06
GTech Headquarters building:                                 September 2006
Hilton Renovation:                                           September 2006
Providence Renaissance Hotel (Masonic Temple):     December 2006
ALCO phase 1 (first 5 buildings - office & retail space):     December 2006
Westin II:                                                        June 2007
Waterplace:                                                August 2007
Hilton parking garage:                                         December 2007
T. F. Green Airport Terminal Renovations:     December 2007
Wickenden St. Comm CTR & Library:            December 2007
Dynamo House & Heritage Harbor Museum:     October 2008
OneTen Westminster:                                  December 2008
Dunkin Donuts Center renovations:               December 2008
ALCO 'final' phases:                                    December 2008
Warwick Intermodal Transportation Center:  October 2009
Empire at Broadway:                                              December 2010

still need:
last phases of the Foundry
Federal Hill condos and hotel proposals (that are more than just rumors)
Parcel 12??
etc.

are those occupancy dates for the condos (waterplace, westin, 110)?

#20 Cotuit

Cotuit

    Megalopolis

  • Global Moderators
  • 13,396 posts
  • Location:State of Rhode Island and Providence Plantations

Posted 03 August 2006 - 02:43 PM

View Postmental757, on Aug 3 2006, 04:27 PM, said:

still need:
Federal Hill condos and hotel proposals (that are more than just rumors)