Accident Fund - Work is continuing on the Ottawa Station and its new annex, mostly interior work is left on both. Construction has finally begun on the new parking ramp.
From February 18th -
Back (East) side of building

Front (West) side of building

Annex (Ionia Building)

From March 30th - (Parking ramp construction)



Lansing City Market -The new market has been completed along with almost $4 million in riverfront improvements. The old market is supposed to be razed to make way for a new $30 million multi use development.

Michigan State Police HQ -The new HQ is now complete and occupied.


MSU Developments -
Eli and Edith Broad Art Museum - Ground was broken in March, foundation work is underway.

Video of Museum fly-through
Facility for Rare Isotope Beams (FRIB)
The new office building has been completed:

The main facility will begin construction in 2013, construction will cost at least $550 million:

Brody HallRenovation is well underway, structure is complete.

College of Nursing The new nursing research building just received Federal funding, construction dates have not yet been announced.

Plant Science Expansion - A new $43 million building to join the Plant & Soil sciences and Plant Biology buildings, construction to begin sometime this year:
Edited by hood, 04 April 2010 - 04:22 PM.