13 hours ago, titanhog said:

Downtown…about how many more feet do you think it will be above the current height of the core?

If indeed the central core is at the 40th floor level, according to the construction documents, there would be 46'-2" to go.. But with the normal core construction being concrete, it would be extraordinarily unusual for the remainder of the fire protected height to be of a different construction type.  If the concrete core is actually topped out, it would be at the level of the roof.  Stairs and elevator enclosures would virtually always extend to the roof level for continuity of fire protection, so if this actually is the top of the concrete, then there is only 5 of 6 feet of the mechanical screen to go above it.  So if the concrete core is really at the 40th floor level, they must have some issue for delaying two additional floors (the 40th and one mechanical floor).  Sorry to rain on the parade if this is the final core height in the photo.

  • Like 3
  • Thanks 1
Link to comment
Share on other sites


3 hours ago, Baronakim said:

If indeed the central core is at the 40th floor level, according to the construction documents, there would be 46'-2" to go.. But with the normal core construction being concrete, it would be extraordinarily unusual for the remainder of the fire protected height to be of a different construction type.  If the concrete core is actually topped out, it would be at the level of the roof.  Stairs and elevator enclosures would virtually always extend to the roof level for continuity of fire protection, so if this actually is the top of the concrete, then there is only 5 of 6 feet of the mechanical screen to go above it.  So if the concrete core is really at the 40th floor level, they must have some issue for delaying two additional floors (the 40th and one mechanical floor).  Sorry to rain on the parade if this is the final core height in the photo.

I’m not sure if anyone is 100% on this being the top.

  • Like 1
Link to comment
Share on other sites

8 hours ago, Baronakim said:

If indeed the central core is at the 40th floor level, according to the construction documents, there would be 46'-2" to go.. But with the normal core construction being concrete, it would be extraordinarily unusual for the remainder of the fire protected height to be of a different construction type.  If the concrete core is actually topped out, it would be at the level of the roof.  Stairs and elevator enclosures would virtually always extend to the roof level for continuity of fire protection, so if this actually is the top of the concrete, then there is only 5 of 6 feet of the mechanical screen to go above it.  So if the concrete core is really at the 40th floor level, they must have some issue for delaying two additional floors (the 40th and one mechanical floor).  Sorry to rain on the parade if this is the final core height in the photo.

I may have miscounted or be completely mistaken, but I think the rising section is currently covering the 40th floor of the elevator core, which would mean that the current top of the core would be the ceiling of the 40th floor, leaving an additional 25’ or so of height for the mechanical floor and the additional screening. 

  • Like 2
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.