This proposal is for apartments and a dual branded hotel.  Demolition on the site has been completed, and this supposedly has a 2016 start date.  But there are/were some legal issues holding up the site plan approval.

magellan4-1.jpg

Magellan1-1.jpg

Magellan2-1.jpg

Magellan3-1.jpg

Austin Design Commission

Share this post


Link to post
Share on other sites


This is awesome news!  This one seemed to have stalled and looked like one of those "next cycle" projects.  But the site plan was approved and released late yesterday.  Developer updates tend to follow approved and released site plans.  Here's the site plan:  5th & Brazos.  The final building details including elevations should be attached to the permit in the near future.

 

Share this post


Link to post
Share on other sites

New information added to the approved site plan shows that three floors were knocked off from the previously proposed height.  Oh well, at least this one is moving forward.  I was ready to write this one off.

Share this post


Link to post
Share on other sites

Here's the new 33-story rendering.  We should be hearing news of a groundbreaking soon (I hope).  

The height reduction came from the podium and a reduced number of hotel levels.   (This was originally proposed as 47-50-stories and later reduced to 37.)  I would have guessed that a height reduction would have been due to a scaling back in the number of apartment levels instead.  This is right off of 6th St. where convenient hotel rooms for drunk tourists are popular.  There is no way in hell I would ever want to live in an apartment any where near that 6th St. mess.  The site has been used as a surface parking lot since the bank building on the site was demolished. 

LHJsNPo.png

Link

  • Like 1

Share this post


Link to post
Share on other sites

There appears to be yet another change in the height of this project.  It was originally proposed as over 500'; then just 400'.  The height was later reduced to 356', but it has now increased to 375'.  Here's the latest elevation from the updated site plan:  

yucZrLD.png

 

Share this post


Link to post
Share on other sites

This project seemed to have stalled late last year.  But this morning retention plans for the excavation were released.  So a groundbreaking must be on the horizon.

Share this post


Link to post
Share on other sites

This project continues to inch along.  A building permit was filed in August to begin construction of Phase I described as the "Pkg Garage Bldg & Open Deck."

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now


  • Recently Browsing   0 members

    No registered users viewing this page.