Huge development news: McLaren Greater Lansing announced this evening that they are consolidating their two south Lansing hospitals, which will allow them an even closer partnership with MSU's College of Human Medicine than before.  The 9-story, 240-bed hospital will include a Karmanos Institue cancer center in addition to the main hospital, and an associated medical office and clinic building.
 

Quote

 

McLaren to build $450 million hospital adjacent to Michigan State

By Haley Hansen and RJ Wolcott | Lansing State Journal

December 4, 2017

LANSING — McLaren Greater Lansing will consolidate operations at its two south Lansing facilities into one $450 million hospital on what was once farm land near Michigan State University, the hospital announced Monday.

 

 

Quote

 

The new health care campus will be developed on land acquired from the MSU Foundation in the foundation's University Corporate Research Park between Collins Road and US 127 south of Forest Road.

Work on the project will begin in spring and should be completed by 2021. The new campus will be paid for through bonds, Mee said.

 

 

This is big news for Lansing since MSU's College of Human Medicine had not really invested in its Lansing home and base.  A big reason for this project is to allow for MSU to be able to better recruit for its home base, nationally, which it hasn't been able to do having divided itself between multiple regional hospitals  They will still partner with Sparrow and such, but this will become the College's flagship campus.

banner_future-lansing.png

Link to comment
Share on other sites

  • 6 months later...

The design-building team was chosen last month.  From the presss release:

Quote

LANSING, Mich. – A joint venture between Lansing-based The Christman Company and Southfield-based Barton Malow will be the construction managers of McLaren Greater Lansing’s new hospital adjacent to Michigan State University. Detroit-based Harley Ellis Devereaux and the Chicago office of CallisonRTKL will be the architects of the acute care hospital, officials announced today.

 

Link to comment
Share on other sites

  • 3 months later...
  • 2 months later...
  • 3 months later...
  • 1 month later...

First steel going up:

30d9a649-e17b-45fb-8455-736651a2ea98-MD7

Structural steel going up at site of new McLaren hospital in Lansing

 

Quote

 

LANSING - Working in a steady drizzle, workers used a massive crane to hoist the first steel column into place for McLaren Greater Lansing's planned $450-million campus in southeast Lansing on Wednesday morning. 

The beam is part of 3,200 tons of structural steel that will be needed to support the nine-story facility in University Corporate Research Park.

All 5,200 pieces of steel should be in place by the end of the year, McLaren officials said. The hospital is on pace to be finished by early 2022.

 

 

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.