On 12/1/2018 at 9:02 AM, DMann said:

It appears that part of the agreement was to build a mountain range on the other side of the river!

 

A source confirms that Crescent is developing 10’000 foot mountains in the River District.  The mountains will be pedestrian friendly.

  • Haha 1
Link to comment
Share on other sites


  • 4 months later...
  • 9 months later...
2 hours ago, KJHburg said:

It is 23 stories 10 levels of office and 1 ground level of retail and the rest is parking.  so I guess 13 levels of parking above the ground level to match the existing mega garage. 

https://www.bizjournals.com/charlotte/news/2019/06/05/honeywell-hq-to-anchor-latest-office-tower-at.html

Thanks.  I thought that it was about ten floors of office.  Do you think that this will top out by Christmas?  Also, the office portion should be well underway by the time the RNC occurs.

By the way, when we will see the coconut palms?

  • Like 1
  • Haha 1
Link to comment
Share on other sites

3 hours ago, SydneyCarton said:

How many floors of office space will there be above the garage?  This is flying up.  I assume that it will top out by the end of the year.

The rate at which they’re building this currently it will top out by the end of this year.  Parking Deck will be complete by May or June.  Assuming they’re able to complete at least two (2) floors per month (average is 2 or 3 per month with Reinforced concrete PT construction) this will be topped out by November or December this year.  

I wouldn’t expect Honeywell would be able to occupy this Tower until June/July of next year (2021) at the earliest.

  • Like 3
Link to comment
Share on other sites

19 minutes ago, Hushpuppy321 said:

The rate at which they’re building this currently it will top out by the end of this year.  Parking Deck will be complete by May or June.  Assuming they’re able to complete at least two (2) floors per month (average is 2 or 3 per month with Reinforced concrete PT construction) this will be topped out by November or December this year.  

I wouldn’t expect Honeywell would be able to occupy this Tower until June/July of next year (2021) at the earliest.

That sounds great.  Thanks!

  • Like 1
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.