7 hours ago, nashville born said:

Question to those who know more about construction.  Why the disparity in progress between the north and south ends?

It could be for a number of reasons, but that's where the ramp is, so that's probably the primary reason. 

They'll place equipment on the slab once it starts to cure, remove the ramp, and use the crane to get equipment down below grade to pour/float the slab. 

 

  • Like 2
  • Thanks 1
Link to comment
Share on other sites

  • 2 weeks later...
  • 2 weeks later...
1 hour ago, markhollin said:

Interesting how the existing ramp on west side above 12th Ave. North that used to be drop-off for previous Valley Arts Building is about 2 feet below the pedestal. 

Gibson, Jan 23, 2022, 4.jpeg

I'm guessing this is the image you are referring to Mark? I wonder if this has something to do with how the dog park area. Maybe it will be built up in some way (drainage reason?) so by the end of construction there really wont be this dramatic of a change in level.

  • Like 3
Link to comment
Share on other sites

  • 2 weeks later...

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.