Does anybody know why they would be spreading out that pad of gravel?  Shouldn't they be taking material out of there for the foundation excavation?

It may be preparation for muddy season to allow ease of use on the construction vehicles. Have we seen a final plan that would show depths, like on the other tower? @downtownresident, @smeagolsfree?

20 hours ago, titanhog said:

Is there a possibility that they are getting ready to use it as a staging area to build 801 first, since it will have a garage?  That way, you already have the building constructed that will allow a parking space for anyone wanting one who will live in 900?

That is a good possibility.

Link to comment
Share on other sites

Just now, Bos2Nash said:

It may be preparation for muddy season to allow ease of use on the construction vehicles. Have we seen a final plan that would show depths, like on the other tower? @downtownresident, @smeagolsfree?

That is a good possibility.

I saw it at one point, but can’t seem to locate the grading permit any longer. 

  • Thanks 1
Link to comment
Share on other sites

They have pulled a construction permit for the construction offices.

AECOM & Giarratana  814 CHURCH ST 101  $250,000.00

Permit #2021001847

Permit Type DescriptionBuilding Commercial - Rehab

Permit Subtype DescriptionGeneral Office, Professional Services

Parcel09305017000

Date Entered01/11/2021

Date Issued02/10/2021

Construction Cost$250,000.00

Address814 CHURCH ST 101

CityNASHVILLE

StateTN

ZIP37203

Subdivision / LotPT LOTS 160&161 ORIGINAL TOWN OF NASHVILLE

ContactJeff Crowley

Permit TypeCACR

Permit SubtypeCAD02B016

IVR Tracking #3913933

PurposeTemporary Offices for AECOM & Giarratana including: metal stud and drywall partitions, acoustical ceiling tile and grid, hvac systems, electrical systems. Build-out of bathrooms is by the building owner under a separate permit and contractor. poc jeff crowley

  • Like 4
Link to comment
Share on other sites

15 minutes ago, smeagolsfree said:

They have pulled a construction permit for the construction offices.

 

So this is the lot where the rehabbed building that had the green banner wrapped around the roof is located.

Does the permit let us know which development  they’re actually getting ready to start first?  900 or 801?

  • Like 1
Link to comment
Share on other sites

1 hour ago, titanhog said:

So this is the lot where the rehabbed building that had the green banner wrapped around the roof is located.

Does the permit let us know which development  they’re actually getting ready to start first?  900 or 801?

That is odd that the Sonder Hotel is the lot that is on the pemit. I wonder if it is actually supposed to be for the Ben West Library lot and Google maps is just off.

A quick look at the parcel viewer even has 814 as the Sonder, so that is very odd. They must  be just leasing space within the building as the permit does say building rehab. 

Link to comment
Share on other sites

  • 4 weeks later...
  • 2 weeks later...
  • 3 weeks later...

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.