Belk Place: Carolina Theater and Hotel Intercontinental


Andyc545

Recommended Posts


  • 2 weeks later...
On 12/20/2019 at 10:30 PM, Hushpuppy321 said:

Looking at where they are now I would estimate this to rise 1.5 floors per month starting in mid to late 1st Quarter 2020.   The pace of construction for the Reinforced Concrete Elevator Core will be the main controlling factor of how fast they get vertical.   Don’t be surprised if this site is only 15 to 20 floors by years end 2020.  

That’s terrible. 

Link to comment
Share on other sites

  • 4 weeks later...
18 hours ago, j-man said:

Why didn’t they work on the theater yearsss ago when things first kicked off?

I believe there was a lot of remediation that was required for the site and the theater. Maybe they are finally at a point where true structural work can begin. 

Link to comment
Share on other sites

18 hours ago, j-man said:

Why didn’t they work on the theater yearsss ago when things first kicked off?

because the fundraising took years. They kicked it off, in order fundraise to do this.

Edited by Guest
Link to comment
Share on other sites

5 hours ago, Rufus said:

I believe there was a lot of remediation that was required for the site and the theater. Maybe they are finally at a point where true structural work can begin. 

Oh ok thank you. Was wondering because I saw where they started the renovations 4 years ago. 

Link to comment
Share on other sites

On 12/20/2019 at 10:30 PM, Hushpuppy321 said:

Looking at where they are now I would estimate this to rise 1.5 floors per month starting in mid to late 1st Quarter 2020.   The pace of construction for the Reinforced Concrete Elevator Core will be the main controlling factor of how fast they get vertical.   Don’t be surprised if this site is only 15 to 20 floors by years end 2020.  

I’m revising this estimate down to possibly only rising 1.5 floors per month starting in mid 2nd Quarter (April or May) meaning only 10 or 12 floors high by years end.  I’m hoping Elevator Core Construction commences within the next 30 - 45 days.  Once that takes off then building floors will begin to rise.

  • Like 3
Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.