On 11/16/2022 at 7:27 PM, GRDadof3 said:

They were adding sections to the crane today. 

Call me crazy, but when I drove by today, it actually looked like it was significantly LOWER than it was before I left a week and a half ago for the Caribbean.

 

(Yes, I'm bragging about being in the tropics while you guys got punched in the jaw by lake effect)

  • Like 2
Link to comment
Share on other sites


On 11/22/2022 at 11:25 PM, Cookin_peacocks said:

Call me crazy, but when I drove by today, it actually looked like it was significantly LOWER than it was before I left a week and a half ago for the Caribbean.

 

(Yes, I'm bragging about being in the tropics while you guys got punched in the jaw by lake effect)

Could someone contribute a photo for comparison? I can't go see it in person seeing as how I'm all the way out here in Japan. :shades:

(but for real I do want to see the progress)

Link to comment
Share on other sites

  • 1 month later...
7 hours ago, Cookin_peacocks said:

Construction has surpassed the existing structure 

IMG20230107094427.jpg

Construction has surpassed the existing structure 

Nice! A bit behind schedule! I thought they had said they’d have 8 floors up by the end of 2022. But excited to see the progress (I’d imagine it’ll start to rise quickly pretty soon.). 

Joe

Link to comment
Share on other sites

I thought I'd be clever and drive to the top of the Studio Park ramp. I didn't make it, and ended up with a lousy photo. Also had to go into the theater to pay for parking, so it ended up being quite a hassle for this: 

As @Cookin_peacocks said, it's above the Acrisure building. I don't see any steel on site. Does that mean they are going with concrete? Seems like they are at the point of floors going up soon (although I think the first couple of floors are the trickiest with the foundation and pool going in first). 

IMG_0479.jpg

Link to comment
Share on other sites

18 hours ago, joeDowntown said:

I thought I'd be clever and drive to the top of the Studio Park ramp. I didn't make it, and ended up with a lousy photo. Also had to go into the theater to pay for parking, so it ended up being quite a hassle for this: 

As @Cookin_peacocks said, it's above the Acrisure building. I don't see any steel on site. Does that mean they are going with concrete? Seems like they are at the point of floors going up soon (although I think the first couple of floors are the trickiest with the foundation and pool going in first). 

IMG_0479.jpg

Yea, this one went the concrete route.

Link to comment
Share on other sites

1 hour ago, Cookin_peacocks said:

That's gonna take a while to build, no?

I beliieve 601 Bond was concrete, and once they got going on the repeatable levels (which I would imagine would be the residential floors above the lobby/pool), it went pretty quickly. So I would imagine it will start to move quick pretty soon.

Joe

Link to comment
Share on other sites

19 hours ago, joeDowntown said:

I beliieve 601 Bond was concrete, and once they got going on the repeatable levels (which I would imagine would be the residential floors above the lobby/pool), it went pretty quickly. So I would imagine it will start to move quick pretty soon.

Joe

Wasn’t the Residence Inn at Ionia and Fulton all precast?  That seemed to move pretty quickly once they got rolling.

  • Like 1
Link to comment
Share on other sites

3 minutes ago, wingbert said:

Wasn’t the Residence Inn at Ionia and Fulton all precast?  That seemed to move pretty quickly once they got rolling.

It was. I think this building might go vertical even faster as the Residence Inn was all pre-cast / they completed an entire level (floor + exterior) before moving to the next. This has a glass facade. But like you said, it went up very quickly once they got past the first two floors.

Joe

Link to comment
Share on other sites

  • 3 weeks later...
  • 2 weeks later...
2 minutes ago, joeDowntown said:

Interesting angle. Can't wait to see how this changes the skyline as it goes up. Also, I imagine that the apartment levels will be very similar, so maybe it'll go much faster from here on out (I'm sure the first two floors were complex + prep work for the entire building. 

Joe

First two floors are going to be like for a pool and likely lobby and other things. Though I'm pretty sure a small lobby already exists on Oakes next to Acrisure 

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

By using this site you agree to our Terms of Use and Privacy Policy. We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.